October 25,1996
M-97-02
MEMORANDUM FOR HEADS OF EXECUTIVE DEPARTMENTS AND AGENCIES
FROM: | Franklin D. Raines Director |
SUBJECT: | Funding Information Systems Investments |
Policy
1. support core/priority mission functions that need to be performed by the Federal government;2. be undertaken by the requesting agency because no alternative private sector or governmental source can efficiently support the function;
3. support work processes that have been simplified or otherwise redesigned to reduce costs, improve effectiveness, and make maximum use of commercial, off-the-shelf technology;
4. demonstrate a projected return on the investment that is clearly equal to or better than alternative uses of available public resources. Return may include: improved mission performance in accordance with GPRA measures; reduced cost; increased quality, speed, or flexibility; and increased customer and employee satisfaction. Return should be adjusted for such risk factors as the project's technical complexity, the agency's management capacity, the likelihood of cost overruns, and the consequences of under- or non-performance
5. be consistent with Federal, agency, and bureau information architectures which: integrate agency work processes and information flows with technology to achieve the agency's strategic goals; reflect the agency's technology vision and year 2000 compliance plan; and specify standards that enable information exchange and resource sharing, while retaining flexibility in the choice of suppliers and in the design of local work processes;
6. reduce risk by: avoiding or isolating custom-designed components to minimize the potential adverse consequences on the overall project; using fully tested pilots, simulations, or prototype implementations before going to production; establishing clear measures and accountability for project progress; and, securing substantial involvement and buy-in throughout the project from the program officials who will use the system;
7. be implemented in phased, successive chunks as narrow in scope and brief in duration as practicable, each of which solves a specific part of an overall mission problem and delivers a measurable net benefit independent of future chunks; and,
8. employ an acquisition strategy that appropriately allocates risk between government and contractor, effectively uses competition, ties contract payments to accomplishments, and takes maximum advantage of commercial technology.
Action Requested
The Budget Legislative Information Management Reform/GPRA Grants Management Financial Management Procurement Policy Information & Regulatory Policy Contact the White House Web Master